Data center pushback in Inver Grove Heights has resulted in a moratorium and an environmental review, but now the developer is pushing back with a $20 million lawsuit. Here’s the latest on the proposed data center:
- Environmental review: In June, a petition from residents forced an environmental review. However, due to the city’s size and square footage of the data center, it was exempt from a required review.
- Moratorium: The Council also approved a moratorium on data centers in June, including the proposed data center. That prompted a lawsuit, and now Council is considering creating an exemption to avoid the lawsuit.
The Lawsuit
The developer, Q’Levr, filed a lawsuit over the city enacting a moratorium after they had submitted their proposal. This not a surprise—they had threatened a lawsuit earlier. Generally, cities can’t change the rules in the middle of a proposal. The lawsuit alleges at least $20 million in damages (earlier threats claimed $150 million).
- Settlement: The city has a settlement offer from Q’Levr. If the city exempts the Q’Levr data center proposal from their moratorium, they’ll settle the suit at no cost to the city. Q’Levr was also willing to abide by a restrictive covenant on the proposed project that would add several measures to address resident concerns, including more vegetative screening, a sound wall, generator testing only during business hours, noise testing, and more. Attorney Jason Kuboushek with the League of Minnesota Cities, who is advising the city, recommended they agree to the settlement.
- Cost: If the city refuses a settlement and loses the lawsuit, $20 million in damages would be well beyond the city’s $1 million insurance cap. Mayor Brenda Dietrich warned that adding $20 million to the 2027 property tax levy could increase a homeowner’s taxes by more than $1,200 or 67%. It would likely take a couple years for the lawsuit to go through the process and it’s unlikely that’s how the city would pay for it, but it is a stark example of the cost of losing the lawsuit.
- Process: Adding an exemption to the moratorium requires three readings. The first reading came at the Monday, August 10 meeting.
The Vote
The initial vote to add an exemption for Q’Levr and allow the data center to move forward failed on a 2-3 vote. Mayor Dietrich and Council Member John Murphy were the lone ‘yes’ votes.
Council Member Tony Scales said he’d be willing to reconsider if public comment could be allowed on the issue at a future meeting. There was no firm agreement on public comment, but Council revoted. Council Members Scales and Sue Gliva changed their votes, passing the exemption 4-1. Council Member Mary T’Kach was the lone ‘no’ vote.
What’s next: The exemption still needs to be approved at two additional readings. The next reading will come at the August 24 meeting. It’s not clear if public comment will be allowed at the meeting, though residents are encouraged to email their comments to the city clerk at cityclerk@ighmn.gov.
More: You can watch this meeting online thanks to Town Square Television.
Aug. 25, 2026 Update: Second Reading Passes
Inver Grove City Council held the second reading of a measure to add an exemption to their data center moratorium that would allow Q’Levr to move forward and settle the lawsuit. About two dozen residents spoke during the meeting, most opposed to the data center.
Council voted 4-1 to approve the exemption, with Council Member Mary T’Kach the lone ‘no’ vote. The measure will come up at the next meeting for a third and final reading.
Sept. 15, 2026 Update: Exemption Passes
Inver Grove Heights City Council approved the final reading of the moratorium exemption, that allows the Q’Levr proposal to move forward. That plan is not completely approved—it still needs to go through site plan review at the Sept. 28 City Council meeting, but this action removes the biggest hurdle.
- Action: While the moratorium is still in place, it no longer applies to the Q’Levr proposal. This also settles the $20 million lawsuit at no cost to the city.
- Next: The site plan review can still include restrictive covenants that puts limits on the Q’Levr data center.
- Vote: The measure passed 3-1, with Council Member Mary T’Kach the lone ‘no’ vote (Mayor Brenda Dietrich was absent). During the vote, Council Member Tony Scales criticized T’Kach, saying they both agree on the issue but the only reason she could vote no was because he voted yes. T’Kach insisted it should be litigated and Scales took issue with her stance.
If you’d like to see local coverage in your community, we need your support. That’s how local news works. Join now to become a member and support local news. Thank you.




2 Responses
I find it interesting that the City has only a $1 million dollar cap on insurance
Like many cities, the insurance is through the League of Minnesota Cities Insurance Trust (which covers 800+ cities), and they appear to have standard caps for varying issues, including “$1 million annual aggregate for land use and special risk litigation claims.” https://www.lmc.org/wp-content/uploads/documents/LMCIT-Liability-Coverage-Guide.pdf